9/26/12: The wrap-up meeting has now been held. This project is now closed.
8/29/12: The PCs were all deployed and operating for the first day of classes. A wrap-up meeting remains to be scheduled, after which the project will be closed.
8/1/12: The PCs are all in place with a working Operating system and requested programs installed. Changes to the new operating system have proved challenging during optimization (dismissing registration and first-run screens); final imaging has been delayed while iterations continue. Final images are now projected to be completed by end of day 8/7/12.
6/26/12: The full 168-PC order has arrived from Dell, been inventoried, and registered on the network. Additional BIOS settings to accommodate remote configuration have made to each machine. Software installation and configuration for generalized image prototyping is continuing, which will then be layered with room-specific software. 25 PCs in Gist Hall 215 and 27 PCs in Siemens Hall 119 have been replaced, and hold an interim image for preliminary testing by ITS. Siemens Hall 118 is expected to be replaced by 6/29/12. Room prototypes should be done by 7/21/12, with imaging occurring the week of 7/22/12.
5/21/12: Prototypes have arrived and the base imaging including software installations has begun. The full order has been placed.
5/8/12: Project approved and scheduled.