08/22/12: Cabling work has been completed, concluding this phase of the project.
08/06/12: Work is in progress on the initial phase of construction. TNS staff are installing new cables and reusing existing cables wherever possible.
05/22/12: A planning meeting has been held to review the summer construction schedule.
04/24/12: Still waiting for work orders to be created.
03/27/12: Waiting for work to be scheduled. Plans have been reviewed with Facilities Design; specific work orders still need to be created.
02/28/12: Per Facilities Planning and Design, the West Gym, 1st Floor & Gymnasium have UC funding approved, the design is nearing completion, and work is expected to start soon.
12/20/11: West Gym Room 201: Plant Ops installing physical improvements. Working with UC on equipment layout and selection. Will coordinate additional utility improvements required for equipment with Plant Ops.
West Gym Refresh: Gym is closed until fall for interior refresh by Plant Ops. TNS will maintain wireless access points.
West Gym 1st Floor Changes: Phase One conceptual floor plan has been approved and design documents are in development. Construction is scheduled for spring/summer.