02/09/2012: Project complete.
01/30/12: The last building to be upgraded, the University Center, is tentatively scheduled for 2/9/12.
12/20/11: Upgrades for the Ceramics Lab, Sculpture Lab and Jolly Giant Commons have been completed. Feuerwerker House is scheduled for 12/22/11.
12/2/11: Upgrades for Wagner House, Little Apartments, Brero House, and Hagopian House have been completed. Ceramics Lab is scheduled for 12/8/11.
10/24/11: Upgrades for Telonicher, Balbanis, and Hadley Houses have been completed. Bret Harte House is scheduled for October 27, 2011.
09/27/11: Telonicher House upgrade is scheduled for September 29, 2011. Thereafter, houses will be upgraded at the approximate rate of one per week.
09/07/11: Upgrades have been completed for three of twelve buildings.