01/15/13: The project is now complete.
12/12/12: The project is nearing completion based on the original scope of work. The Forbes Complex (now Wellness Center) renovation was also added to the project scope after the project began, resulting in a 1-2 week delay. At this time, the project is 92% complete with only SH remaining.
11/19/12: The project continues to make steady progress, with GH, HC, and FH now completed.
10/26/12: The project continues to make slow but steady progress, with LB, TA, FR, and other buildings being completed; the project is now 45% complete. The entire project is expected to be completed by 12/3/12. Ongoing delays are the result of a shortage of available electricians.
10/05/12: The project has beenmoving forward with about 1-2 pathways being readied by electricians each week. TNS has been following behind the electricians installing the network cabling. As of this update, the following buildings have been cut over: WFB, BSS, K&A, SERC, NR, SC, VMH; the project is now 31% complete.
9/24/12: The project has started, but could be late because of a lack of available electricians.
5/8/12: Project approved and scheduled.