04/22/13: Working on scheduling After Action Review.
03/28/13: Project is now complete except for the After Action Review.
03/22/13: ITS technical resources are not yet available, and the new testing start date has moved from 4/2/13 to 4/15/13. The production installation date has been set for 5/1/13 - it needs to be completed in time for the Spring 2013 Registrar's grade processing.
02/25/13: Item 1 (Repeat checking), Item 2 (Changing RP grades after 1 year), Item 5 (Exclude failure due to dishonesty grades from Repeat checking), and associated run controls will all be installed into production by 3/13/13. Item 3 (Incomplete contracts and RP grades) was cancelled because it would have required significant PeopleSoft baseline customization. Item 4 (Incomplete grades automation) remains to be completed once ITS technical resources open up. We expect to begin testing on 4/2/13.
01/28/13: Repeat Checking (customization #1) is done. Awaiting status on testing the impact from the CO's ESP Use of 'RP' Grade (see December 2012 memo) (customization #5), development of remaining requirements (estimated completion was end of January), and estimated move-to-production date.
12/13/12: Customization #1, Repeat Checking, will go into production on 12/20/12. The balance of the customizations will be ready for testing by the end of January and a go-live date will be selected at that time.
11/26/12: Once the registration business cycle is complete, the programmer will be provided guidance by the responsible functional individual. The production rollout date will be discussed at the 12/4/12 project team meeting.
10/29/12: The modification was approved, so we are now awaiting the programming schedule from the programmer lead.
9/24/12: Nothing to report this month, as we continue to await a business decision regarding the preferred proposed technical solution to present to the Mod Governance Committee.
9/06/12: We are waiting on a business decision regarding the preferred proposed technical solution to present to the Mod Governance Committee.
8/06/12: Technical analysis is expected to be completed by 8/10/12; the team will then look at the various options and propose a solution for Mod Governance Review. At this time, we will also re-evaluate the availability of ITS resources and the project schedule.
6/25/12: Project team kick-off meeting held 6/7. More information needed about the requirements and potential solutions before setting a go-llive date. The team will regroup this week and review tasks and timing. Additionally, the August peak business cycles conflict with the requested go live date, but a September or October go-live would be workable. Schedule change can be mitigated by communicatons to faculty from the Registrar's office and ITS Management was already aware of potential changes.
5/8/12: Project approved and scheduled to start 6/1/12.