The B.O.S. accepted the report by Co. Engr. A. J. Logan, that the Bull Creek Rd is completed. Also the B.O.S. accepted the report by Logan that the wood truss bridge at Korbel is done and the concrete road from Fernbridge to Ferndale is completed. Section 3 of the Lord-Ellis Rd under constr. is 90% done. The B.O.S. instructed the Clerk to advertise for bids for section 4 which is 3.9 miles long and would complete the road to Green Point. This section should be completed by Aug. 1, 1920.