background 0background 1background 2background 3

Immigration Rights and Resources for the Campus Community

Exercising Your Rights to Free Speech

Contract confirmed by HBMWD for annual payments by G-P & Simpson Paper for $144,000 each

DT Data Page #: 403

Newspaper: Humboldt Times

Newspaper Date: 9/24/1959

Page #: 1

Item Type: Contract

Place: Ruth Reservoir

Text: The HBMWD confirmed that G-P and Simpson Paper company signed contracts which call for annual minimum payments of $144,000 by each firm. That insures construction of the Ruth Reservoir project =$10,750,000 which will begin next March. The HBMWD formed on March 13, 1956. The contracts call for delivery of water by July 1, 1962 and run until 1999. The 131' foot high dam will cover 1,150 acres. The district has secured water rights to 130,000 A.F/yr.

Key Words: Ruth Reservoir Project, Contract, Hbmwd, Annual Payments

Microfilm Call # : MF 10