Progress report on construction of rr

DT Data Page #: 301

Newspaper: Humboldt Times

Newspaper Date: 9/22/1912

Page #: 1

Item Type: Railroad work

Place: Island Mountain Tunnel

Text: Progress report on construction of the RR. The Island Mountain Tunnel - 3,000 ' feet done of total 4,400' feet. Work has started on the steel bridge at the south portal. Work on the grade both north & south of the tunnel is being pushed.

Key Words: Construction, Island Mountain Tunnel